No I mean the universal formula for work.
Work = duration x assigned number of units to the task.
Assigned units can be as 5 men, 6 trucks,
so the work then will be man hours or truck hours etc.....
but why does MS project display it as hours only....
hour is duration. Work is not duration. it is how long certain amount of resource worked for it = duration x assigned units
|