Quote:
Originally Posted by ketanco
But the formula for work is
work = duration x assigned units
this is a universal formula
|
I fear we may have a mismatch in terms. What do you mean by "assigned units"? In MS Project the assignment of resource at x% of their time is the assignment element. This is measured in % of the resource's time
What are you referring to when you say "assigned unit" which you see as measured in hours?