Hi everyone,
When you save a baseline anywhere on baselines 1-10, does the 'last saved' date stamp always appear with the baseline where it was saved?
See the baselines list pic I shared. I just inherited this project scheduled in Microsoft Project. Although date stamps are only with Baseline and Baseline 1, many of the other Baselines (2-10) also have data in them (I mean baselines saved in them). Is this normal?
I am using Microsoft Project Professional 2019. The schedule is accessed from server through Project Web App.
|