I want to define two constraints for each of my tasks, namely "No Earlier Than" and "No Later Than". I couldn't find such settings. How is it possible to have secondary constraints for a task?
The only way I could see to do this would be to have the task under a summary task which is driven by the "no earlier than" date as a milestone. Each task would then have a "Start no later than" constraint.
Can I ask why you need these constraints?
HTH
Miles