Ok, if the start dates is actualized as indeed started and you are only updating the finish date, and your successors are linked finish to start they should indeed move the same duration as the driving predecessors 'push', this is assuming you are accounting for the work days on your assigned calendar. Of course days will be added to your successors to account for weekends if you are using a 5 day calendar.
|