Help with Resource Allocation in MS Project
Hello,
I need help with Project. I am creating a go-live schedule and want to use a resource only once a week and want project to tell me if i am over allocating them. Each task is for 4 hrs and i changed the resource to 10% thinking if assign it to another task the same week it would flag, however, project is using a resource 10% for each task. I am attaching an example Project File.
Would appreciate if someone could guide me here.
Thanks,
B
|