Identify Active Predecessor
Hi,
I am new to ms project and I am creating a timeline, I was hoping there was a way to easily identify what predecessor is driving the schedule when there are multiple predecessors on one task.
eg.
36SS,24FS+4 wks,35SS
It would bold, or underline or someway show that the one task is driving the schedule and the others are not.
Thanks in advance!!
|