Project Schedule with multiple calendars
I am working a schedule that have multiple calendars including standard - 5x8's (40hrs per week), & 6x12's (72hrs per week) schedule.
The beginning of the project, workers will be working on the standard schedule and the remaining of the project, they will be working on the 6x12's schedule.
I have created the new project 6x12's schedule and was able to assign these calendars to each task, but the "Work" hours were not calculated properly. Example, I have 2 units of one resource for 2 days during the 6x12's schedule, but the "Work" column is still calculating the hours based on Standard schedule which will show 2 units x 8 hours/day x 2 days = 32 hrs instead of 48 hrs.
Any advise to correct this?
|