Hi,

I would like to create a final chart with the appearance of this image. Those two lines would be a SUM of to custom fields, defined in resources as number type, based on the resources assigned to each task in a precise moment.

Those values are not a cost but a value of risk by doing some cumulated tasks.

So, I’ve created the two custom fields in resource tables, with test values, and assigned the resources to several tasks, but when a try to make a Excel chart from Ms Project, I add those resource fields (number10, number11) as custom fields but they never appear in excel cube data for select.

Do you know if this is the right way to go? Is this possible to do with Ms Project?

P.S. I'm using the Project 2007 version.

Thanks in advance.


Last edited by jtorres; 03-15-2011 at 05:18 AM. Reason: correct image tag
Reply With Quote