Default Changes from Gantt view to Detailed Gantt View

I have added data to create a Gantt Chart. I have entered durations, and successors and predecessors. The Gantt chart reads fine, however when I changed to a Detailed Gantt View it removes most (not all) of the predecessors and changes most of my durations to 1 day. I have all tasks set for as soon as possible and the task mode is set at Automatic for all tasks. Help!?