Thread: Custom Report
View Single Post
 
Old 10-11-2019, 03:42 AM
Yosemite Yosemite is offline Windows 10 Office 2019
Novice
 
Join Date: Oct 2019
Posts: 1
Yosemite is on a distinguished road
Default Custom Report

Hi All

Looking at the attached sample mpp, Can anyone provide input to a custom report that will show the total number of days and cost per discipline i.e. Mechanical between each phase of the schedule?

for example...

Phase 0:
Mechanical Durations = 2 days
Mechanical Costs = £960

Electrical Durations = 1 Day
Electrical Cost = £480

Phase 1:
.....

Phase 2:
.....

Phase 3:
.....

Phase 4 could be a bit more difficult as there are multiple resources selected.
How can this be split out to show the same as Phase 0 above?

Any help is much appreciated.
Attached Files
File Type: mpp Sample.mpp (278.5 KB, 5 views)
Reply With Quote