Custom Report
Hi All
Looking at the attached sample mpp, Can anyone provide input to a custom report that will show the total number of days and cost per discipline i.e. Mechanical between each phase of the schedule?
for example...
Phase 0:
Mechanical Durations = 2 days
Mechanical Costs = £960
Electrical Durations = 1 Day
Electrical Cost = £480
Phase 1:
.....
Phase 2:
.....
Phase 3:
.....
Phase 4 could be a bit more difficult as there are multiple resources selected.
How can this be split out to show the same as Phase 0 above?
Any help is much appreciated.
|