Question How to create a Man Hour Resource with fixed durations and fixed Work

I am trying to create a Man Power curve with my schedule.
I have a known duration, and a total Man Hours for each task.

I am trying to see how many men per day on average is required to achieve this?

How would I go about achieving this?