Hi all,
I´m really get stuck in the resource sheet. Hope, you could help...
I have some human resources which are only partly in the project, not the whole duration/year. I can set the from/to properly in the resource property sheet: from 01.04.2019, until 31.12.2019.
Now, I showed both colums in the overall resource sheet too. But there, project displayes in field from "NV" and in field until "31.03.2019". I have no glue, why
. If I enter availability from 1.1.-31.12.2019, project displays the correct values in resource sheet.
There are no date limitations on project level nor on task level. No task has an dedicated resource yet. It is the same behavoir, if I create a totally new project.
It´s project 365, current version 2016.
Do you have an idea?
-rosebow