Take out the WBS links- they are bad practice, and make problems like this a lot more likely. It should always be tasks linked, a WBS is a cover all for other items, and as such has no actual presence.
There is no reason you cant have a milestone at the end of a WBS as a task and use this, but the actual WBS xauses more problems than anything else.