Hello all,
New to the forum...
First Question, I need a column that I can input a number in hrs format, that will rollup, and will not change, unless I change it manually, I was using Work and renamed it "Budget" which sort of works, however, Project will change it as the duration changes.
I tried Baseline Work, but that did not work because once the number was set, I could not change it again and have it continue to rollup with out having to reset the baseline.
I think I need a macro Number column that includes the "hrs" with the number, and will allow to rollup in the Formula Custom Field.