Calculating the duration of a task based on work rate
Hello,
- we are manufacturing desks in batches.
- every batch has different number of desks
- we schedule our work per batch and not per desk. for example: Task1: Batch 11, 34 desks
is it possible to calculate in ms project the work needed for the task (34 desks) if i know the work needed for the production of one desk?
thank you in advance
|