Default Creating report showing only part of work from one resource at a task with more resources working at

Hello together,

I'm totally new here and a beginner in MS Project. I use MS Project 2016 Professional and want to create my own report.

In this report I want to have a table with the fields Name, Ressource Initials, Baseline Work and Actual Work. The tasks are filtered for a special space of time and for one special resource. What I now want is to see, how many work this person offered to the task. The problem is that I can't show only the work in hours according to this person I filtered. Always I get the overall hours from all persons attached to this task.

Unfortunately I didn't find any answers for my problem while searching with google. I hope you can help me, how to create such a table.

Thank you,

Daniel