Default Inactive task: bug with a lag?

Hello,
I use a lot the command "inactive tasks" which permits me to reschedule the project so that all subsequent tasks are moved forward based on the “removal” of the inactive tasks.
But if a task has a precedessor with lag time and you try to inactive it, it seems that the next task "feels" this lag and is not rescheduled.
I attached an example file: if you try to inactive the task "E", task F doesn't follow the end of task D as I would like.
How can I resolve it?
Regards
Codeghi