hi all,

i have a MS Project 2013 project c/w resources including their costs, but am hoping to set up a report (or filtered column) that will give me their costs (for cashflow purposes) within a given date range.

i can use the reporting function to do it by week number using the Task Usage report, but our billing month is from the 21st of one month to the 20th of the next, ie: 21 Sept to 20 Oct.

i can see the total project and task costs easily for the total project using the Costs column, but not for the date range.

Any suggestions please?