Linking tasks between projects error
Hi,
I am trying to link a task between 2 projects but get thie error:
"There is a problem with the entry. The accrual choice is not valid. Type Start, Prorated, or End"
I created the initial project schedule and then 'saved as' to another name. e.g. pr1 saved as pr2.
In pr2 I am trying to link to a task in pr1 by typing in the full address in the Predecessor space. e.g.
C:\MyProject\Project Schedule\pr1.mpp\114
|