Default Project Calendar for Shutdowns / Turnaround

I am using MS Project 2016 for Planning of Shutdown of 15 Maintenance Days having Calendar of 24/7.

I have developed resource sheet in MS Project 2016 but I want to know what calendar shall I use as a base for Resources as labors used in day and night shifts having same craftsmanship but their quantities will be different in both shifts.