Default Link activities and milestones between projects (2003)

Hi,
have screened the current subjects concerning the area but without any luck. I am looking for clear guidance to get dependencies working between sub projects.

As I have seen, today I only find info around linking to a master project (which I also use) but I thought there would be ways to linking between sub projects.

How do you for example handle if milestone1 in sub proejct A goes into sub project B with a number of activities and the end up in Milestone 2 that deliveres back to sub project A?

Thanks for feedback!