Experts please help!
Please help. I'm very new to MS Project and have been asked to set up a QA Project resource alignment effort.
Essentially I need one Project that shows:
Each project on the annual alignment:
Project Name
Projected available QA Start date
Projected QA End date
= (Available duration in days and/or hours)
QA Estimate/Effort in hours
Assigned QA resource(s) for each project
QA Start Date
QA End Date
Assigned daily QA hours to the project
To show:
- Hours remaining to QA
- Hours remaining of QA
In addition - a place where each analyst can update daily hours spent on QA
to provide % complete. (Hours performed vs. QA est./effort)
In the end to show allocation (annually) by project and/or resource.
So I was thinking of creating a Parent task which is essentially the project "Project 1" with sub tasks "Project 1 - Resource 1" and "Project 1 - Resource 2".
This way I could do a report on the task Project 1 or tasks %Resource 1
I really hope someone can help! Thanks in advance.
|