Hi, I need to help. I want to add 2 column, 1 is Duration 2 is Finish
View Single Post
06-07-2017, 02:18 AM
Redulman
Windows 7 64bit
Office 2013
Novice
Join Date: Jun 2017
Posts: 1
Hi, I need to help. I want to add 2 column, 1 is Duration 2 is Finish
1. For "Duration" must be: 26751/3600=7.43 day and with formula roundup. result 7.43 to 8 day.
2. For "Finish" must be: start(31.05.2017)+8day=08.06.2017 (saturday workday)