Thanks Julie. I can see that the Total Slack unit is the same as the unit that the Duration has been entered in but I want the Total Slack to be shown in "days" for every task irrespective of what the Duration unit is. Is this possible? and if not, is there a quick way to convert all the Duration values to "days" without manually changing each one?
|