Default Display an additional date column in Gantt chart

Hello,

I am new to MS Project, and I need help with displaying an additional date column in the Gantt chart.

I have the Start Date and Finish date and one additional column which is the Schedule date. I could get the bars to display for the start and finish dates, but now I want to display the Schedule date too, which could be somewhere within the range of start & finish dates or in the future.

This is for about 200 rows of data, which represents 200 projects. The main purpose is to see the start, finish and the schedule dates for each project.

I tried adding this Schedule date as a milestone through Bar styles, but its not displaying anything.

Thanks!