Impossible to make a daily project
I'm trying to make a daily project in MS Project 2016. It stars and end every day. It repeats every day.
I cannot make it because Projects keeps trying to assign it a specific date.
I cannot copy the end date of any task to link it with another date of another task, because it uses the date at which I created the first task, and then assigns hundred of hours to the task length, when it should be minutes.
I need Project to ignore any specific date, and only take in consideration the hour. How do I do it?
|