I'm afraid the best option is a work around. Create a task with a duration of one minute - set it as the success to task 1 - predecessor to task to and apply the successor calendar to the task. But, the next question is why are you applying so many task calendars? Give us some more insight into the "whys" and we'll tro to be more helpful.
|