as workarounds, there might be a couple of solutions
you could export the durations to excel, multiply by the number of units required, then paste back into project (taking out any summary durations- they could make a mess otherwise.)
the other would be to put a resource against each task (use the same one, doesn't matter what it is) then reduce to 10% for 10 units. this would multiply the time required by 10 for each activity.
As Julie said, Project doesnt do it- it works with what you give it.
|