I'm sorry, but I don't understand your question. If the tasks are linked, the finish date of the project may be recalculated by resource leveling as long as the option "level only within available slack" is not selected. It is also possible that resource leveling did not delay any critical path tasks and it was not necessary to delay the project finish date.
|