Hello.

On the beginning sorry form my English.

I just stared work with MS Project.

My question is :

When i have task A (start on 13.03 and finish on 15.03 -3days ) and task B and i am setting dependency to task A Ms Project automaticity setting start date as 15.03.
I can't understand that . if I set 3days that is 13/14/15 then next task should start automatically at 16.03 not 15.03.

Please help