Yes, there is a gap created by a -20 days predecessor between task #3 and task #4. The completed task (#3) is in the past and the next task (#4) is in the future.
The thing that creates the strangeness for me is the fact that nothing within the summary task is late and yet the summary task is marked as late...
|