Default displaying start and finish times as absolute numbers instead of dates

Hi all,

Does anyone know how to customise the Early Start, Early Finish, Late Start and Late Finish fields so that in the columns they display as they number of days/weeks/months since the project began. In other words, suppose I haven't decided on a start date for the project yet, but what I'm interested in seeing is the total number of days/weeks/months needed to complete the project.

If the above is possible, then my follow-on question is - how does one change the network diagram so that it displays the Late Start and Late Finish fields as well?

Thanks,
Benson