Default Resource Overallocation Reporting

I currently use Project 2007 and will be upgrading to 2010 soon. I currently have a master resource pool shared among approximately 30 projects. Under the master resource pool, it is a simple matter to look at individual resource allocations.

What I have been unsuccessfully trying to do for the last two days is to produce a visual graphic of multiple resource allocations vs. time. My intent is to create a visual dashboard of my staff that allows me to quickly see specific periods (by quarter) where my staff is overallocated as opposed to having to go through each resource via the resource graph view in Project. I want to be able to printthis visual for the benefit of my superiors.

I have tried custom visual reports to no avail. I seem to be able to only pull work totals. I have tried exporting the data but am having trouble finding the correct table from which to pull work hours vs. time. Any assistance you could provide would be great.
Reply With Quote