Default Question regarding filter:marked as late

I have a strange thing in the filtered view of tasks when I apply the filter Late tasks.

One summary task is marked as late as seen in one of the screen shots attached.

The task that creates this "late date", is a milestone marked as 100% complete in the project.

The only thing I can see that could be the cause of this is the constraint task-20 days, but I do find it strange that it should create a late warning since its complete?
Attached Images
File Type: jpg marked_as_late (Medium).JPG (42.8 KB, 18 views)
File Type: jpg marked_as_late_project (Medium).JPG (63.1 KB, 18 views)
Reply With Quote