Question regarding filter:marked as late
I have a strange thing in the filtered view of tasks when I apply the filter Late tasks.
One summary task is marked as late as seen in one of the screen shots attached.
The task that creates this "late date", is a milestone marked as 100% complete in the project.
The only thing I can see that could be the cause of this is the constraint task-20 days, but I do find it strange that it should create a late warning since its complete?
|