Quote:
Originally Posted by JulieS
If that is the work field, display the Project Summary task and it will show the sum of the work. On the Gantt Chart Tools Ribbon, click the checkbox to display the project summary task.
|
Thank you for your answer.
The Project summary task shows me the needed time from beginning to the end.