Hi
As already suggested you can hide the start and finish columns from your view. In addition you can change the Timescale view on gantt portion of your view to show only week Numbers or Month Numbers as opposed to actual dates. Activities must have start and finish dates with Predecessors dependencies to actually be able to schedule all activities in the correct order.
Simply right-click in the date portion of the Gantt Chart view and select the options you want to see for each Level (Top, Middle, Bottom).
Hope this helps.
|