Leveling resource not resolving issues
View Single Post
02-11-2017, 12:51 PM
JulieS
Windows 10
Office 2016
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Setting priority to 1000 means "Do not level". So the resource leveling command in Project will not attempt to level those tasks.