Activate the chart.
Right click and Select Data.
Choose Start and press Edit.
Change the Series Values reference as required.
OK.
Same procedure for Duration.
If you un-merge row 3 and 4, put your headings in B4:E4 and make B4:E24 an Excel Table the chart will automatically adjust in case of more tasks.
|