I'm not sure that the Physical % complete ties in with actual work values. The Earned Value is either calculated from % complete (duration) or physical % complete - but not % work complete. When I create a simple project and set things up to use Physical % complete as the earned value method (both the field and the calculation), updating Physical % complete has no effect on Actual Work. The actual work values remain zero.
|