Thread
: [Solved]
Project does not distribute work evenly between the days
View Single Post
01-09-2017, 06:01 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Is the task Fixed Duration? Does the resource have a special working calendar? Is the task manually scheduled?