Default Fixing Work, % of actual work and Final Date in a task (while assigning resources)

Hi,

I am trying to fix work, % actual work, and final date on an activity while assigning and removing resources, the only column I want to to change is the initial date of the activity. I also have already a percentage of actual work done which should be constant also.

The problem is that whenever I assign/remove a resource, the percentage of work done goes to 0% (other times it changes initial or end date) - I canīt make any sense of this.

Thanks you in advance for your help.

Happy new year.