Is there an elegant simple way to create cost projections in Microsoft Project?
View Single Post
12-28-2016, 11:48 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Set the tasks as fixed duration. Assign the resources and enter the work when you assign the resource. (I'd use the Task Form shown in the lower pane). It will calculate the cost based upon work (per resource rate * work).