Default Project Calendar - working days have varying hours

Hi,

I'm about to work with a new client whose working time each day varies - its fair to say their working hours are non-standard as below.

Monday is 8am to 5pm
Tues to Thurs is 7am to 5pm
Friday is 7am to 3pm

Before I start to work them I've been thinking about how I could accurate capture duration data on projects plans that we will be developing going forward.

Its a given that I need to align the settings in the 'Calendar options for this project' with the project calendar, otherwise durations and work estimates could be wrong or inaccurate.

So, given this non-standard shift pattern, how best should I reflect the working hours in the calendar options to ensure symmetry between the two.

Thanks in advance for your help.