View Single Post
 
Old 10-31-2016, 05:45 AM
jaywizz1 jaywizz1 is offline Windows 7 64bit Office 2010 32bit
Novice
 
Join Date: Mar 2016
Posts: 2
jaywizz1 is on a distinguished road
Default Creating a task similar to Working Time exceptions

Folks I have a project that for a period of 2 weeks there are a range of activities that I cannot undertake but there are some that my team can be getting on with.

Ordinarily I'd add a Work Exception to prevent any tasks being scheduled but this is not practical in this instance.

So I have simply scheduled a single task to block out 2 weeks and then attached some tasks to this manually. This works in general but when the schedule starts to move I then have to go back through the entire task list and tweak which tasks are now related to this blocked out time and which tasks have had this relation nullified.

Has anyone any ideas?
Reply With Quote