Quote:
Originally Posted by jkdiesel
I have a basic project set up with multiple levels of sub tasks under one summary tasks. (see photo attached). The thing I cant figure out is this:
using 168004 (green summary task) as an example, I have one project (a 91 day) that started and finished in January 2016. Another project (pmi support) started in july. How can I make the green summary task ONLY show the total days I actually worked, and not the total span from the start of the first one to the end of the second one.
|
Have you considered showing the Work field to show much work was actually accomplished during the duration? As you have discovered Duration <> Work. The duration counts the number of working days between the start of the earliest subtask to the end of the latest subtask. You can have a situation where there are large gaps between subtasks that will be reflected in the summary task duration. However, the work for the subtasks will be summarized correctly.