Sorry for the delay. I am traveling without my Project 2016 machine available. My suggestion, create a custom table with the fields. Copy the table to the global template (Global.mpt). Apply that table to each of the subprojects and make sure you also have that table applied to the master project.
Is it possible that you've switched fields (Text1, Text2) in some of the subprojects?
|