View Single Post
 
Old 08-19-2016, 05:14 AM
Frank144 Frank144 is offline Windows 7 32bit Office 2013
Novice
 
Join Date: Aug 2016
Posts: 1
Frank144 is on a distinguished road
Exclamation Adding work converted to actual automaticaly

We are currently experiencing some issues with Project 2013. Whenever we create a task and add work in the future (adding the work on a specific day or week), it sometimes generates actual work at the same time. Since changing the actual work has been deactivated through EPM, PMs don’t have access to correct these issues when it occurs.

Is there is a way to prevent the actual time to be generated when adding work on a task?
Reply With Quote