Thread: [Solved] Assigning number of days
View Single Post
 
Old 07-15-2016, 05:23 PM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Set the task as Fixed Duration and enter 5 weeks duration. Split the screen to show the task form. Under Resource Names, select the resource and enter to 400 hours of work. Project will calculate the Peak Units and spread the 400 hours of work out evenly over the 5 week duration.
Reply With Quote